INTRO

Project Description

SeaWorld San Diego had an existing fuel system that needed updating. Western Pump removed one (1) 10,000 gallon UST system and replaced it with one (1) AB-2481 continuously monitored 10,000 gallon UST system with double wall sumps, product, vent, and vapor piping, electrical controls and monitoring. The project was completed March of 2021 and included demolition, underground tank replacement, backfilling, dispenser replacement, fuel management installation, start-up and commissioning.

Underground tank installation.

DETAILS

Project Features

  • One (1) 10,000 gallon underground storage tank
  • One (1) 10,000 gallon AB-2481 Continuously Monitored UST Addition
  • One (1) Gasboy 9800 Series twin hose, twin product, gasoline/diesel dispenser
  • New Veeder-Root sensors and probes
  • Fuel System Electrical
  • Fuel Management System
  • Testing, Start-Up, and Commissioning
Underground tank installation.
Underground tank installation.
Tank installation.

Services Provided

  • Procure Equipment
  • Demo
  • Tank Removal
  • Tank Installation
  • Fuel System Electrical
  • Tank Monitoring System
  • Drive Slab Installation
  • Dispenser Installation
  • Flow Meter Calibration
  • Fuel Management Installation
  • Crash Protection
  • Start-up & Initialization
  • Regulatory Inspections