Project Description

Western Pump has completed a raze and rebuild of an older Love’s Travel Stop in Buckeye, AZ.

The project included excavation, trenching, backfill, fuel system installation, electrical testing, start-up, and commissioning, as well as lube equipment installation, testing, start-up, and commissioning.

A Picture of Love's Travel stops gas station

DETAILS

Project Features

  • Auto Fueling Area – One (1) 30,000-gallon regular unleaded single-compartment Underground Storage Tank (UST) and One (1) 20,000-gallon two-compartment Underground Storage Tank (UST) (12k Diesel / 8k Premium Unleaded Gasoline)
  • Diesel Truck Fueling Area – One (1) 20,000-gallon single-compartment Underground Storage Tank (UST) (Diesel Exhaust Fluid), One (1) 6,000-gallon single-compartment Oil Water Separator and Four (4) 12,000-gallon UL-2085 Aboveground Storage Tanks
  • Seven (7) Multi Product Dispensers (3+1 Blenders)
  • Six (6) Master/Satellite + DEF Dispensers
  • Four (4) turbine tank sumps
  • Underground Pipe Installation
  • Back Fill Tank and Pipe Excavation
  • Tank Monitoring System Equipment
  • Testing, Start-Up, and Commissioning
  • One (1) owner provided Lube Tank
  • Ten (10) medium pressure Oil Pumps
  • One (1) Grease Pump
  • One (1) Waste Oil Pump
  • One (1) 10 Reel Mounting Bracket
DCIM100MEDIADJI_0201.JPG
DCIM100MEDIADJI_0190.JPG

Services Provided

  • Saw cut, breakout, remove concrete
  • Tank Installation
  • Piping Installation
  • Fuel Dispenser Installation
  • Tank Monitoring System Upgrade
  • Drive Slab Installation
  • Flow Meter Calibration
  • Lubrication System Installation
  • Start-up & Initialization
  • Regulatory Inspections
  • Close-out Documentation