Project Description

The new Love’s Travel Stop & Country Store located in Westmorland, CA. Western Pump was selected to construct the Fueling Systems for this project. Scope of work included all mechanical and electrical control systems, conduits, and wiring for the installation of a large auto and truck stop facility. Project included four (4) Underground Storage Tanks (USTs), four (4) Aboveground Storage Tanks (ASTs) with underground piping and electrical for thirty-four (34) fuel positions under two Canopies.

DETAILS

Services Provided

  • Fuel System Permitting
  • Excavation & Trenching
  • Engineered Slide Rail Shoring Embeds
  • Pipe Supports
  • Tank Installation
  • Fiberglass Piping Installation
  • Black Iron Steel Piping Installation
  • Submersible Pump Systems
  • Centrifugal Pump Systems
  • Secondary Containment
  • Fuel System Electrical
  • Tank Monitoring System
  • Tank Pad Installation
  • Drive Slab Installation
  • Flow Meter Calibration
  • Decals & Signage
  • Start-up & Initialization
  • Regulatory Inspections
  • Compliance Testing
  • Record Drawings
  • Operation & Maintenance Manuals
  • Close-out Documentation

Project Features

  • Four (4) 30,000-gallon Underground Storage Tanks (USTs) with Deadmen
  • Anchoring Systems
  • One (1) 6,000-gallong Oil/Water Separator
  • Four (4) 12,000-gallon Aboveground Storage Tanks (ASTs)
  • One (1) Tanker Truck Unloading Station
  • Six (6) 10-HP self-priming centrifugal Pump/Motor Assemblies
  • Eight (8) Submersible Pump Systems
  • One (1) Junge Biodiesel Blend System
  • Seventeen (17) Under-Dispenser Containment (UDC) Sumps
  • Seventeen (17) Metal Island Forms
  • Nine (9) Multi-Product Fuel Dispensers in the Auto Fueling Area
  • Eight (8) High-Flow Diesel Dispensers in the Truck Fueling Area
  • Three (3) Remote Diesel Fill Stations
  • Product/Vapor/Vent Piping Systems (above and below ground)
  • Fuel Management, Leak Detection, and Monitoring Systems
  • In-Station Diagnostics (ISD) System